Contract Information Class 1 |
| Reference Number |
IPD2025_025. |
| Amount Payable |
Greater than $150,000.00 $ 20,970,568.81 (incl GST) |
| Effective Date |
07/07/2025 |
| Completion Date |
09/12/2026 |
| Name and business address of the contractor |
Shape Australia Pty Ltd - Level 11, 155 Clarence Street Sydney NSW 2000 AUSTRALIA
|
| Particulars of the project to be undertaken, the goods or services to be provided or real property to be leased/transferred |
Liverpool Civic Place - Liverpool Campus Expansion works |
| Details of any related body corporate or private sector entity who will be involved in carrying out any of the contractor’s obligations or receive a benefit. |
|
| Are there any provisions under which the amount payable may be varied? |
Yes |
| Amount Payable Variation Clauses |
Refer relevant Clauses Refer relevant Clauses 47 48 49 50 51 52 53 54 55 57 58 59 60 61 62 63 64 65 67 73 74 75 76 77 |
| Can the contract be renegotiated? |
Yes |
| Renegotiation Clauses |
Refer relevant Clauses Refer relevant Clauses 47 48 49 50 51 52 53 54 55 57 58 59 60 61 62 63 64 65 67 73 74 75 76 77 |
| Did the contract involve a tender process? |
Yes |
| Tendering Method |
Selected Tender Invitation |
| Tendering Criteria |
Mandatory Completeness Check plus Price and Non-Price Criteria: Programme; Project Methodology; Appreciation & Understanding of the project; Companys relevant Experience; Key personnel & resourcing; Proposed Consultants & Sub-Contractors; Notifiable Incident History |
| Description of any provisions under which the contractor is to receive payment for providing operational or maintenance services |
N/A |
Contract Information Class 2 |
| Is there a transfer of significant assets to the State? |
No |
| Is there a transfer of significant assets to the contractor? |
No |
| Has any cost-benefit analysis been undertaken by UOW? |
Yes |
| Cost Benefit Analysis Results |
A formula was used to compare the submissions from the five tenderers to give an average weight and ranking, |
| Was a public sector comparator used? |
No |
| Did the contractor provide a base case financial model? |
No |
| If relevant, provide details of how risk is to be apportioned between the parties. |
N/A |
| Have there been any significant guarantees or undertakings between the parties? |
Yes |
| Details |
2 x Bank Guarantees for 2.5% of contract value |
| Other Key Elements |
All standard clauses as per GC21 and Special conditions. |
Contract Information Class 3 |
| Is a complete copy of this contract included in the register? |
No |
| Details of the reasons why all or part of the contract has not been included in the register |
Please contact the Information Compliance Unit to access a copy of the contract at icu-enquiry@uow.edu.au. |
| Details of whether the contract or any provisions will be included at a later date and if so, when |
See above. |
| General description of the types of provisions that have not been included in the register if some but not all of the provisions of the contract have been included |
See above, |
| Contract |
|